Jun 1, 2004 12:00 PM, By Don Sturgis
The Factory Acceptance Test or FAT (sometimes called a Pre-Shipment
Test, System Test or more recently Integration Test) was originally
used for all kinds of custom-built systems to work out design
and manufacturing flaws, and to prove that a system will do the
job it is supposed to do before it is shipped to a customer site.
After satisfactorily completing a factory test, a system is typically
disassembled and shipped to the customer site, then reassembled
and subjected to a Site Acceptance Test (SAT), which would replicate
all or some of the FAT, with the expectation of getting the same
test results.
Manufacturing control systems, telephone switching systems and
electric power distribution control systems — to name just
a few — undergo factory tests that take weeks and involve
dozens and sometimes hundreds of people for their execution. Preparation
for that type of factory test takes months. In contrast, a properly
planned and executed FAT for a large security system usually takes
1-3 days, and the planning and preparation only a few weeks.
Security system Factory Acceptance Tests
When electronic security systems were first developed, and as
they continued to grow in capability and complexity, a FAT was
needed to ensure that new aspects of systems would work correctly
when the components were connected and the system was set up for
use. For most access control systems in the 1980s and ‘90s,
the time intervals between feature changes and bug fixes were
often measured in weeks. A FAT was required to make sure that
bugs had not crept into the systems along with intended enhancements.
Because the systems were not integrated at the time, a separate
FAT needed to be conducted for each type of system (access control,
alarm monitoring and CCTV).
As the reliability of electronic security systems increased,
and as the time intervals between changes lengthened, it became
common to use a FAT only if the customer required or requested
one. Typically, the only customers who requested them were those
already familiar with factory tests, or whose security or engineering
consultants knew of their importance.
Information technology accelerates change
Today's large networked and computer-based electronic security
systems are more encompassing and more complex than previous generations
of systems. They are usually an integration of multiple systems
from one or more manufacturers. The high pace of technology change
means that, in essence, many system integrators will never install
the exact same system twice. More frequently, a systems integrator
is now building systems using components or applications that
the integrator has not previously installed in the same combination.
Thus, a FAT should be included in the plans for any large physical
security system and should be indicated as a major milestone for
acceptance and payment.
Factory Acceptance Test
Many installing technicians are not familiar with factory acceptance
testing. If they were, they would require it regardless of the
customer's preference because of the tremendous benefits to the
installing vendor. Vendor personnel who have not performed a true
Factory Acceptance Test often try to omit it. They try to convince
the customer that it is costly and time-consuming, asserting that
the testing would be a waste of time, since they know their products
well and everything works the way it should. However, the FAT
offers the customer the only opportunity to witness major operational
issues of the system and to work out flaws in the design before
any equipment is shipped to the job site. These flaws can show
up in many different ways — whether improper component selection;
“bugs” in custom software applications; or interconnectivity
or integration issues. What better place to find these issues
than in a controlled environment at the “factory”
where it does not interfere with or compromise any activities
at the customer site?
The FAT brings the hardware and software together for testing
in one location prior to shipment to customer sites, in order
to:
- demonstrate the suitability and workability of the system
design;
- verify correct interconnectivity of all system components
showing that hardware and software are fully integrated as a
system;
- satisfy capacity and performance requirements that are not
demonstrated in previously installed vendor's systems;
- prove compliance with specifications, and confirm that all
custom requirements perform as specified;
- verify that critical performance parameters operate as described
in the functional requirements and/or design specifications;
- verify that backup and restore operations function as required;
and
- verify that redundant server takeover operations function
as required.
The FAT can be performed only after the system design has been
completed. System design means more than just selecting equipment
and determining device counts. It includes working out how the
customer will use the system. Some examples:
For access control systems, it includes developing the access
levels for assignment to system users, something that may require
collaboration with the customer's security and human resources
departments.
For video monitoring systems, it includes determining how the
automatic camera control will be used in response to alarms, what
events will initiate video recording, and how other video system
features will be used.
For ID badging systems, it means designing the actual badge types
and preparing to print real badges.
The customer and vendor must collaborate on these tasks. Cooperation
ensures that there are no misunderstandings about how the system
will operate, and in some cases, the customer may be able to obtain
free improvements and customizations. At the least, system setup
is significantly accelerated because without a FAT these issues
typically would not be addressed until the system is being installed.
The customer can even participate in the data entry as part of
the FAT setup, thus providing hands-on experience with the system
before it is installed. Furthermore, key customer personnel who
will serve supervisory roles involving the security system can
receive basic training to prepare for their participation in the
testing process. Educated test participants will speed up the
testing process, and the more the customer knows about the system,
the more comfortable he or she can be in terms of system acceptance.
MDI Security Systems, Rancho Cucamonga, Calif., a manufacturer
of access control, alarm management, digital video and digital
audio systems, offers a Factory Acceptance Test as a separate
line item on the majority of its proposals. Most MDI systems are
sold through dealers or system integrators, so it is up to these
“middle-men” to convince the end-user of the value
of the FAT. Most are convinced and purchase this option.
“The end-users like the FAT because it gives them a chance
to touch-and-feel the equipment and to get training on it before
it is installed at their facility,” says MDI senior vice
president Ray Payne. “Some customers even bring along [the
system operators] who will be working with the system on a day-to-day
basis. We get their inputs on what they like and what seems to
be difficult for them. We have made improvements to the systems
based on some of their comments.”
Payne indicates that the dealers and integrators like the FAT
because it gives the end-user an opportunity to buy in and take
ownership of the system during these tests. “The best value
for [the manufacturer] is realized in the case when something
isn't working correctly after the system is installed. The dealer/integrator
is less likely to blame the equipment but more likely to assume
that the operator is doing something wrong because they saw the
system working correctly here at our facility,” Payne says.
“Another advantage to the dealers/integrators is if they
have turnover in personnel, it gives their newer technicians an
opportunity to work with the system before they have to install
it in the field.”
Frequently, the FAT is not conducted at the “factory,”
but at the system integrator's facility. Regardless of where these
tests are performed, the main advantage is that all components
of the system are in one room or area of a building instead of
being dispersed over the end-user's multiple sites.
When the tests are performed at the manufacturer's site, as in
the case of MDI, the dealer/integrator comes to the factory a
few days before the end-user to help set up the system. They then
do a first run-through of the tests to find any problems and correct
them before the customer arrives. The technical personnel who
are capable of correcting any design issues normally work at the
“factory” and can witness the anomalies first-hand.
They can instantly see how performing a task at one “site”
impacts the operation at another “site,” since all
equipment is assembled together. They can then immediately delve
into solving the problems without ever having to leave the test
site or send out field personnel.
This is much more cost-effective and provides a more timely solution
than the alternative. If no FAT is performed the system integrator
incurs the cost of technical personnel traveling to the end-user's
facility to deal with these same issues after the system has been
installed. Solving these problems in the field always involves
more calendar time and vendor expense, and will inevitably delay
the date when a fully functional system can be turned over to
the end-user. A well-designed and executed FAT will pay for itself
in both time and money.
Optimizing test scope
For very large systems, it is not practical (and sometimes not
even possible) to assemble, connect and configure every piece
of hardware and software that will be installed. Thus a minimum
configuration should be designed that will accomplish the objectives.
When some of these objectives can be proven for various aspects
of the system, by reference to existing customer sites (with the
same models and versions of the system components), it is not
necessary to prove them again in the FAT. In particular, this
approach can be used to satisfy the maximum system capacity and
performance requirements, and reduce the number of hardware devices
required for the FAT.
Furthermore, proving that one piece of equipment (such as an
access control panel) meets the maximum capacity requirement is
sufficient to prove that all panels can meet that requirement.
However, the overall capacity of the system to handle the intended
full equipment load and the message traffic it generates must
still be proven.
For complex systems, it can make sense to perform the FAT in
stages. When complex subsystems are providing simple inputs into
the main system (such as a fence-line perimeter intrusion detection
system), it is only necessary to demonstrate the ability of the
main system to accept and process these inputs. The subsystem
operation can be verified as a separate stage, either before or
after the main system factory test, by reference to existing customer
sites or by separate testing. This approach works if a subsystem
is ideally tested in a physical environment that is not conducive
to the main FAT test. For example, testing a five-mile fiber optic
network backbone is best done at the network systems factory location
rather than at the system integrator's facility.
Some specialized pre-shipment tests must also be performed separately
because they involve harsh or specially controlled environments
and may need to be performed over an extended time period. For
example, outdoor security system components that will be installed
at oil refineries or chemical processing facilities must be resistant
to the airborne chemicals in those environments and may have to
be enclosed in explosion-proof housings. Some marine facility
security system components must withstand corrosive salt sprays.
In such cases, laboratory-certified test results — or inspection
of existing customer sites — should be used to eliminate
the need for customer testing.
Scenario-based testing
A system integrator's customer list will contain a wide variety
of facility types. The exact uses of the security systems from
facility to facility will vary, meaning acceptance tests should
be tailored to fit the way each customer needs and wants to use
the system. This is where security scenarios come into play.
A scenario is a sequence of events that a customer expects to
take place as his system is used. There are two categories of
scenarios: normal operations and security response. Security response
includes investigation of suspicious indicators as well as responses
to security incidents.
To develop security scenarios, examine the jobs, roles and activities
of each person who will be using the system. For access control
systems, that includes system operators as well as system users
(the people who will be granted access privileges). Often 6-12
scenarios can cover most system usage requirements.
In general, factory testing consists of a list of features that
must be demonstrated, along with the steps required to demonstrate
them and the results that should be observed. A single scenario
will include the use of multiple system features. By performing
the scenario-based tests first, the customer will be able to mark
most features as tested, and then address the remaining individual
features as necessary.
Scenarios should include (as appropriate for the system):
- alarm operations;
- surveillance operations;
- badge issuance operations;
- access control operations;
- reporting operations;
- emergency mode operations; and
- backup and restore operations.
The customer provides the security scenarios and seeks assistance
from a security consultant or even from the vendor in the development
of the scenarios. Regardless of who prepares them, the security
scenarios are an important primary responsibility of the customer.
A discussion of security scenarios is not complete without making
this important point: Acceptance testing is not limited to the
security scenarios. The customer is not responsible for writing
the test plan or designing tests. The purpose of scenarios is
to ensure that both the customer and the vendor understand how
the customer intends to use the system.
Factory Acceptance Test plan
Test plans will vary from system to system. In general, the testing
should be planned in order to provide a realistic and adequate
exposure of the system to all reasonably expected events, given
the system's scope and purpose.
Using the IEEE Standard 829 for Software Test Documentation as
a guide, an acceptance test plan should include in detail:
- description of the scope and approach of the test;
- references to related documents (such as specifications, user
guides, etc.);
- types of tests to be carried out;
- features and combinations of features to be tested;
- features not to be tested (and the reasons why);
- test environment;
- system equipment including model and version numbers;
- test setup requirements;
- test pass and fail criteria;
- test suspension and resumption criteria;
- any test equipment and tools;
- staffing training and skill requirements, and responsibilities;
- schedule for test performance and all test-related tasks,
including post-test reports;
- any risks requiring contingency planning;
- a list and description of test deliverables (IEEE Standard
829 requires the following documents: test plan, test design
specifications, test case specifications, test procedures, test
item transmittal reports, test logs, test incident reports,
test summary reports); and
- the names and titles of all persons who must approve the test
plan
Once the overall test plan is approved, the individual test cases
(also called test scripts, test procedures or test suites) can
be developed. Completing the up-front work of test planning (as
listed above) speeds the creation of test case development. A
common error is to grab a features list or specifications document
and to start writing test cases as the first action. This approach
inevitably becomes a stop-and-go activity, as the test designer
will encounter many questions along the way that must be answered
before test case design work can be continued.
Who writes the test plan?
Ideally, test plan templates would be written by the manufacturers
and tailored by vendors and customers for each system being tested.
Vendors should incorporate the integration aspects of the systems
in their test plans, and, over time, build up their own library
of reusable test templates. The customer should have final say
over the test plan.
Payne indicates that MDI has prepared FAT guidelines for its
systems and individual features and makes them available to assist
dealer/integrators in preparing the actual test plans. Emil Marone,
chief technology officer for Henry Bros. Electronics, Saddle Brook,
N.J., agrees: “Since we know the customer's needs, we, the
integrator, must take the manufacturer's guidelines or test scripts
and tailor them into a Factory Acceptance Test that demonstrates
the features of the system the customer requires. The customer
(or customer's security or engineering consultant) needs to be
involved in this process and buy off on the final test plan. The
test can then be performed by the customer alone or jointly by
the vendor and customer.
“I cannot stress too strongly the need for the customer's
input during the entire process (from clarifying expectations
for the system, through design, and to development of the Factory
Acceptance Test),” Marone continues. “Our most successful
installations have been the result of a close working relationship
with the end-users. Having the customers supply us a person or
personnel totally familiar with their operational needs is the
key to providing the correct system. This aids in creating the
proper Factory Acceptance Test, the purpose of which is to ensure
they receive a system which meets their needs.”
Test results
Obviously the best scenario for a Factory Acceptance Test is that
all tests perform as planned and the system is shipped and installed
on schedule. The worst-case scenario is that there are one or
more major issues that do not perform as required and cannot be
resolved by the vendor within a reasonable and acceptable time
period. If the purchasing contract is written correctly, the customer
has the option at that point of canceling the contract. Given
today's level of technological advancement of both systems and
vendor personnel, that situation is unlikely.
In between these two extremes are the following situations that
are more likely to occur.
Both vendor and customer agree that an issue does not meet its
expected test results but are able to agree on an acceptable solution.
The “fix” is incorporated, the system is retested
and performs as planned. In this case the customer gets the desired
system — the only negative effect is the system ships later
than scheduled because of the time required to find and implement
the “fix.”
Both vendor and customer agree that some performance issue does
not meet its specified requirements. As an example, the specifications
state that an alarm message must appear on an operator's screen
within 2 seconds from the occurrence of the alarm. The tests show
that this time is typically 3 to 4 seconds and there seems to
be no way to improve it. The customer must now decide whether
this is such a significant issue as to reject the system or to
accept the system with its lesser performance criteria. A third
solution is that the customer conditionally accept the system
with the agreement that the manufacturer will correct the performance
issue and provide the required corrections to the installed system,
at no cost, within an agreed-upon time frame.
If the test cases are not well-written, the customer and vendor
may interpret the results differently. The vendor may state that
the test results meet the intent of the customer's specification;
the customer may disagree. Questions regarding the validity of
test procedures or test results should have been resolved in the
earlier customer review and approval of the test plan; however,
it can happen that the test procedures or test results were interpreted
differently by the vendor and customer, and the difference does
not become apparent until test time. That is another benefit of
the FAT: it can bring such differences to light before installation
occurs.
Test scheduling
Best practice dictates that the vendor actually perform a practice
run of the entire test, step-by-step as it will be executed by
or for the customer. This is a good way to flush out errors or
inaccuracies in the test procedures. It also provides the vendor
with knowledge of how long each test procedure actually takes,
so that groups of tests can be scheduled accurately, and test
breaks can be included in the schedule at appropriate intervals.
NOTES
Factory Acceptance Test Checklist
A successful Factory Acceptance Test should have the following
features:
- Is described clearly in a well-written test plan
- Is documented accurately by well-written test procedures
- Is prepared by inputs from manufacturers, vendor, customer
and/or security consultant
- Must be quantifiable and verifiable
- Must include all tests for major system design and integration
issues
- May include special test software or hardware to simulate
high traffic volume not easily implemented any other way
- May include special test software or hardware to create test
specific conditions or events that must be repeatable across
several test scripts
- Be sufficiently detailed so that the end-user can verify the
test setup and perform the tests
- Is run by the customer, or run by the vendor with customer
participation and/or observation
- Has its individual tests approved or disapproved (pass/fail/pass
with conditions) as performed by one or more customer personnel
or customer representatives
FOR THE RECORD
About the author
Don Sturgis, CPP, is a senior security consultant for Ray Bernard
Consulting Services (RBCS), a firm that provides high-security
consulting services for public and private facilities. This article
is excerpted material from the upcoming book The Handbook of Physical
Security System Testing by Ray Bernard and Don Sturgis, scheduled
for publication by Auerbach Publications in the spring of 2005.
For more information about Don Sturgis and RBCS go to www.go-rbcs.com